Mbongozi

MBONGOZI HYDROELECTRIC  PROJECT

The Mbongozi Hydropower Project is more than just a power generation scheme; it is a bold step towards addressing Malawi’s growing energy demands, reducing reliance on fossil fuels, and accelerating socio-economic development. Designed with a total installed capacity of 41 megawatts, the project involves the construction of two hydroelectric power plants, one with a capacity of 16MW and another with 25MW.

Strategically located along the Bua River and its tributary, the Chimbwazi River, the project’s infrastructure is as innovative as it is comprehensive.

The project comprises several key components:

  1. Two Earth Dams: One at Mphindapasi on the Bua River, and the other at Chimbwazi on the Chimbwazi River.
  2. Interconnected Waterway System: A canal/tunnel will link the two dam sites, allowing optimal water management and flow regulation.
  3. Powerhouse and Turbine Base: These facilities will house high-efficiency turbines designed to harness the energy of flowing water with minimal environmental impact.
  4. Spillways and Reservoirs: Designed to manage seasonal fluctuations and ensure safe, reliable power generation.
  5. Electrical Infrastructure: This includes the installation of generators, turbines, transformers, a substation, a switchyard, and the laying of transmission lines to integrate with the national grid.
  6. Control Unit & Admin Office: For on-site operational management and remote monitoring capabilities.

The project is being developed through a public-private partnership model, with support from international development agencies, private investors, and the Malawian Government. Key financing is expected from a blend of concessional loans and climate finance mechanisms, recognizing the project’s alignment with global clean energy goals.

 

Timelines and Progress:

  1. Feasibility and Environmental Impact Assessments: Completed in early 2024
  2. Design and Engineering Phase: To be done in 2025
  3. Construction Commencement: Expected in late 2025
  4. Commissioning of First Plant (16MW): Targeted for 2027
  5. Commissioning of Second Plant (25MW): Scheduled for 2028